Stay up to date on all the progress we're making on our land by checking out the photos below!

On a mobile device?
For best viewing choose landscape mode. Tap anywhere on the image to progress to the next, or use arrows to navigate.
 

February 9, 2017

Auditorium, Commons, Children's Building


February 1, 2017

Exterior walls, atrium finishes, AVL in the Worship Center


January 12, 2017

Main Entrance, Baptistry, Auditorium


December 12, 2016

Exterior walls, terrace, commons


November 17, 2016

Interior walls, risers, and auditorium


November 9, 2016

Auditorium progress and external wall


October 23, 2016

Writing On The Foundation Event


October 17, 2016

Commons Slab is Poured and Exterior Wall


September 13, 2016

Canopy, Auditorium and Children's Building


August 24, 2016

Progress on the roof and commons


August 3, 2016

Auditorium walls go up! 


July 26, 2016

Walls on the Children's Building and stage pour


July 19, 2016

First wall goes up! 


June 29, 2016

The auditorium floor is poured in the middle of the night! 


June 27, 2016

Trucks arrive to finish pouring the walls


June 23, 2016

Structural steel goes vertical for the children's building! 


June 18, 2016

First wall of our building is poured into the casting bed!!


June 9, 2016

Casting beds for west wall of the auditorium are poured! 


May 24, 2016

Casting beds for Children's Building are poured


April 26, 2016

Stage wall is poured!


April 14, 2016

Stage and parking lot progress


April 8, 2016

North & West parking lots and the Children's Building slab


March 15, 2016

The first parking lot is poured! 


February 4, 2016

One of our two entrances off of Mt. Gilead is poured


January 10, 2016

Groundbreaking Event


January 4, 2016

Early stages of construction